- Walls and ceilings are finished in the entrance, cafe, nursery and toilets
- All lights are fitted in these areas
- Door frames are in for these areas too (and doors in some cases)
- Floors are in the toilets
- Cubicles are built in toilets and sanitary ware is partially fitted
- Main Auditorium walls are painted, second coat going on tomorrow
- Main Auditorium wall lights are fitted and working
- Main Auditorium ceiling has been started
- Air conditioning units have been fitted
- Kitchen walls and ceiling are finished
So, as you can see... a busy couple of weeks!!