Work continued leveling the site and clearing away the tonnes of soil, rocks and trees. By the end of the week the footings had been dug and reinforced concrete had been placed into the left hand side and rear footings.
Still a long way to go but by the end of next week it should be easy to see the footprint of the new building.
New Life Revival Church Building project - North Wales. New community center for Colwyn Bay.
Tuesday 26 May 2015
Monday 18 May 2015
17 May - End of Week 13
The site has now been leveled and is ready for digging the foundations and footings. Tonnes of material needs to be removed from site including trees but progress is steady.
Next week we should start to see the shape of the foundations take place, the footprint of the building.
Next week we should start to see the shape of the foundations take place, the footprint of the building.
The project is slightly behind schedule but it is hoped to recover this lost time over the next few months.
Wednesday 13 May 2015
13 May - Week 13 - Ground works start
Well after a few weeks work has finally started on the site. This is it, the foundations are being dug out ready for our new building! So, here are some pictures from the site this week and regular updates will follow now.