Thursday 25 June 2015

25 June - Week 19

Sorry for the late update but I couldn't get to site!

However, it's worth the wait because now you can see part of the sub floor in as well as all four walls. You get a real sense of the shape of the build with the curved front walls.

I've tried a different video technique this week to get better quality video, especially for those that can't get down to the site...enjoy.










Friday 12 June 2015

12 June - End of week 17

Good progress has been made this week and now you can really see the shape of the foundations taking place.  You can even see where the frame is going to go if you look carefully!

You may be wondering where the front of the building is... well they need to pull in loads of concrete soon so they're leaving the front wall until all the concrete has been bought in.

Once the walls and floor are done the frame can start.












Monday 8 June 2015

7 June - End of week 16

The weather hasn't been amazing this week with strong winds and heavy rain but progress continues steadily. Three walls are now being built and we're starting to get a feel for the shape of the building.

"All the people gave a great shout of praise to the Lord because the foundation of the house of the Lord was laid." Ezra 3:11












Monday 1 June 2015

31 May - End of week 15

Work has continued digging out the footings on the North side of the plot whilst on the South and East side foundations have started to be built.

This is always the hardest part of the build, lots of work going on but very little to show for it!  The rest of the trees have been removed though and the footings and foundations are starting to take shape.